Impossible to determine final costs of National Children’s Hospital says health minister Stephen Donnelly

España Noticias Noticias

Impossible to determine final costs of National Children’s Hospital says health minister Stephen Donnelly
España Últimas Noticias,España Titulares
  • 📰 businessposthq
  • ⏱ Reading Time:
  • 48 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 22%
  • Publisher: 71%

Minister was responding on Friday as costs set to top €2 billion

Health Minister Stephen Donnelly has insisted that “nobody could accurately” put a figure on the final cost of the new children’s hospital and accused Sinn Fein of being used as “pawns” to justify overspend.

Last week, it emerged the planned handover date from the contractor BAM is to be pushed back from March next year to May, while the cost of the hospital is spiralling. The minister said the Government was supporting the board in its engagement with BAM for what he described as “a world-class children’s hospital”.

A total of 1,478 claims had been decided, at a value of €14 million, and worth less than 2% of the overall contract value. He said Sinn Fein’s finance spokesperson had claimed that young people were emigrating over the matter. “They want change. They want better for themselves, their family and the children of this State. They want the children’s hospital built.”Asked if he would be comfortable with BAM receiving other high-profile Government contracts, Donnelly said it will be important to allow the State to consider “previous performance” in the awarding of future large-scale infrastructure contracts.

Hemos resumido esta noticia para que puedas leerla rápidamente. Si estás interesado en la noticia, puedes leer el texto completo aquí. Leer más:

businessposthq /  🏆 8. in İE

España Últimas Noticias, España Titulares

Similar News:También puedes leer noticias similares a ésta que hemos recopilado de otras fuentes de noticias.

National Children’s Hospital: Surging costs linked to ‘build-as-you-go’ planningNational Children’s Hospital: Surging costs linked to ‘build-as-you-go’ planningJust 27 rooms at the National Children's Hospital have been completed out of a target of 3,000
Leer más »

Just 27 rooms at National Children’s Hospital finished out of 3,000, committee hearsJust 27 rooms at National Children’s Hospital finished out of 3,000, committee hearsThe cost of the National Children’s Hospital could surpass €2 billion according to a detailed breakdown of figures presented to an Oireachtas committee, while just 27 rooms have been completed out of an expected 3,000.
Leer más »

Only 27 of 3,000 rooms at National Children's Hospital are complete | Her.ieOnly 27 of 3,000 rooms at National Children's Hospital are complete | Her.ieBack in 2015, construction costs for the National Children's Hospital (NCH) were estimated to come in at around €600 million. It is much, much higher now
Leer más »

Tánaiste concedes 'real difficulty' surrounding cost of National Children’s HospitalTánaiste concedes 'real difficulty' surrounding cost of National Children’s HospitalTánaiste Micheál Martin was responding to a question by Sinn Féin’s health spokesperson David Cullinane during Leaders’ Questions in the Dáil today.